Ferrous Chloride and Dosing Plant

This project included the manufacture and installation of a two tier custom built distribution board and remote IO panel and three local control panels. The site installation included isolations and cutovers into the existing electrical installation with upgrades to the existing local MCC at Luggage Point Sewage Treatment Plant.

The project was 4 months in duration and consisted of a 6 person work crew including the management of our control systems sub-contractor and machinery and plant.

The technical challenges experienced on this project were a short time frame provided by the client and delivering during the height of the COVID 19 lockdown measures of April and May 2020.