Final Settling Tanks – Fulton Hogan

This project included the complete electrical and control systems renewal of Final Setting Tanks 9 to 12 at Luggage Point Sewage Treatment Plant.

The complete electrical  design and installation was renewed with the manufacture and installation of a three-tier custom built switchboard and associated local control panels on each tank. The site installation included isolations and cutovers into the existing electrical installation with upgrades to the existing local MCC feeding tanks. 

The project was 12 months in duration and consisted of a full project life cycle from design through to installation and commissioning.

The technical challenges experienced on this project were undertaking the works whilst maintaining plant operability.